  • The Form Work of Pillars of the Makara Thorana continued
  • Casting of Walakulu Bemma on the South Boundary wall continued
  • Continued cutting & polishing of Marble. Final touches of Steps continued
  • Continued repairing of Louvers of windows
  • The Pillars of the Makara Thorana concreted
  • Casting of Walakulu Bemma on the South Boundary wall continued
  • Continued repairing of Louvers of windows
  • Continued cutting & polishing of Marble. Final touches of Steps continued
  • A rainy day. No work done
  • Continued repairing of Louvers of windows
  • The Form Work of Pillars of the Makara Thorana continued
  • Casting of Walakulu Bemma on the South Boundary wall and Plastering of North Walakulu Bemma continued
  • Replacement of roof tiles started on Resource Center
  • Continued cutting & polishing of Marble. Final touches of Steps continued
  • Continued repairing of Louvers of windows
  • Casting of Walakulu Bemma on the South Boundary wall started. North Walakulu Bemma plastering continued
  • Continued cutting & polishing of Marble. Final touches of Steps continued
  • The Form Work of Pillars of the Makara Thorana started
  • Continued repairing of Louvers of windows
  • Pagoda Base concreted
  • Continued cutting & polishing of Marble. Final touches of Steps continued
  • Partitioning of Bathrooms & toilets continued
  • Continued repairing of Louvers of windows
  • Plastering of Walakulu Bemma on the North Boundary wall continued
  • Work delayed due to rain
  • Beams of the Makara Thorana concreted
  • Bar bending work of the foundation of the Pagoda continued
  • Continued cutting & polishing of Marble. Final touches of Steps continued
  • Partitioning of Bathrooms & toilets continued
  • Continued repairing of Louvers of windows
  • Plastering of Walakulu Bemma on the North Boundary wall continued
  • Continued the door fixing in side of the Right wing building